3-20 Bench Setup and Operation
SG4000 Installation and Operation Manual
Figure 3-18 illustrates the forward segmented 4X board.
Figure 3-18
Forward segmented 4X board
Figure 3-19 illustrates the signal flow through the forward segmented 4X board. Loss is
measured at 870 MHz.
Figure 3-19
Forward segmented 4X – signal flow
Rx
Rx
Out
Out
Loss = 2.7 dB
To set up the forward segmented 4X option:
1 Confirm that an SG4-R/* receiver is installed in lid optics slots 1, 2, 7, and 8.
2 Confirm that two forward segment 4X boards are installed in forward configuration board
locations 1 and 4, as illustrated in Figure 3-17.
3 Connect an RF cable from each SG4-R/* to the inputs of the forward segmented 4X boards.
The RF cable should be approximately five inches long and have black boots on the
connector signifying the forward path.
4 Connect the appropriate forward RF cables from the SG4-RF modules to the forward
segmented 4X boards.
In a typical installation, the RF modules in Ports 1 and 3 are connected to the forward
segment 4X board in configuration location 1. The RF modules in Ports 4 and 6 are
connected to the forward segment 4X board in configuration location 4.
5 Ensure that the PIC cable is properly connected to the lid router board and center power
distribution board in the housing base.
6 Route the fiber service cable into the node and fiber tray.
7 Measure the optical input power on the forward fiber pigtails, leaving enough length to
connect them to the receiver bulkhead connectors.
8 Connect the service cable pigtails to the receiver bulkhead connectors.
9 Apply power to the node (see Powering the Node in this section). Allow five to ten seconds
for the system self-diagnosis to complete.